RWE completes foundations and export cables Triton Knoll

Sustainable energy

United KingdomRWE has taken a huge step towards first power generation in 2021 at Triton Knoll by completing the installation of all 90 turbine foundations and two 50-kilometre long export cables connecting offshore and onshore electrical systems.

The installation was achieved during one of the project’s most challenging times due to the impact of Covid-19, and has been completed within the planned summer delivery window. With a commercial operation date expected in the first quarter 2022, Triton Knoll wind farm will have an installed capacity of 857megawatts (RWE’s pro rata share: 509 MW), capable of supplying green electricity equivalent to the annual demand of over 800,000 UK homes.

Triton Knoll offshore wind farm is located over 32 kilometres off the Lincolnshire coast. It is jointly owned by RWE (59%), J-Power (25%) and Kansai Electric Power (16%), with RWE leading the wind farm’s construction and long-term operation and maintenance works, on behalf of the project partners. Total planned investment volume amounts to approximately £2 billion.

Power purchase agreement

Triton Knoll was awarded a Contract for Difference (CfD) by the UK Department for Business, Energy & Industrial Strategy in September 2017. A Power Purchase Agreement (PPA) with Ørsted, under which the company will offtake 100% of the power produced by the wind farm, complements Triton Knoll’s CfD, mitigating any market price uncertainty for the first 15 years of the wind farm’s operation.

RWE has significant experience in the UK offshore market with nine wind farms in operation. Further offshore development projects, like the 1.4 GW Sofia offshore wind farm – 100% owned by RWE – underline the growth ambitions of the company in this country.